Propel NY Energy moves to construction after state regulators clear two key plans
New York Transco and NYPA secured approval for drilling operations, though the exact start date for work in New Rochelle remains ambiguous.
By Grace Kim ·

Propel NY Energy advanced to the construction phase on November 19 when the New York State Public Service Commission approved two critical plans for the transmission project. The commission’s decision clears the path for horizontal directional drilling at Hudson Park and Beach in New Rochelle and along Shore Road in Oyster Bay. These approvals represent the first two regulatory steps for the roughly 90-mile underground and submarine transmission line.
New York Transco and the New York Power Authority, the project developers, announced the approvals and contractor selections in a release on November 20. The project aims to strengthen electrical connections between Long Island, New York City, and Westchester County. Completion is scheduled for 2030, following an estimated four-year construction period.
The approved plans authorize the preparation of shoreline connections for submarine cables that will cross Long Island Sound. The Crossing Group will perform the horizontal directional drilling for the crossing between New Rochelle and Glen Head. Hallen Integrated Construction Services will assist with the drilling, while LS Cable & System will supply and install the submarine cables.
A discrepancy exists between the project’s published schedule and recent announcements. The Phase 2 fact sheet lists two windows for drilling at Hudson Park: November 2026 through April 2027, and again from November 2027 through April 2028. However, the November 20 announcement stated that initial construction is anticipated to begin early next year, with more active work expected in mid-2027.
The approved Phase 2 plan addresses temporary construction areas, equipment staging, truck traffic, lighting, and noise mitigation. It does not specify how many parking spaces will be unavailable or whether beach and marina access will be restricted. The plan also lacks details on the duration of specific disruptions for Hudson Park residents.
New Rochelle has already accepted financial compensation related to the project. In October, the City Council approved a $430,000 advance payment from NYPA for easement interests at Hudson Park and Beach. The city retained the right to seek additional compensation. The proposed 2027 budget projects $4.3 million in easement revenue for 2026, compared with $40,000 for 2027, with most of the 2026 figure attributed to Propel NY Energy.
The New York Independent System Operator reported on November 17 that the project will provide substantial reliability benefits to the state grid. Without the project, Long Island could face transmission reliability deficiencies as early as summer 2030. The NYISO also found that a statewide electricity resource deficiency would occur one year earlier and be approximately 550 megawatts larger without the transmission line.
Project developers estimate that construction will support approximately 2,000 jobs annually and generate $2.4 billion in regional economic activity. Joris Veldhoven, president of New York Transco, stated that the recent approvals demonstrate the project is ready to move toward construction. The next public webinar is scheduled for December 15 at 6 p.m., where representatives will provide updates and explain new public information tools.